Finished oiling Deck , landscape pebbling and paver strips today
Deck now ready for NexDome
Latest update from Sidereal is Deck should arrive in Melbourne docks tomorrow, 7 - 10 days to clear Customs and then delivery to place on the South Coast
Due to COVID and a design upgrade the Dome has taken around 8 months from order to delivery on site ( normally 4 to 5 months from Canada )
Hope to have it up and running mid to late March
Fingers crossed
Attached Thumbnails
Click for full-size image (9A4E9E83-89E2-4F74-8C36-3C996C859410.jpeg)
159.4 KB161 views
Click for full-size image (4F75B409-3FD1-4269-B965-A27C8E0F50C7.jpeg)
198.9 KB125 views
Click for full-size image (D8332ED1-022B-43F6-9085-EEA1A311A348.jpeg)
195.3 KB122 views
Click for full-size image (B9F438C1-80D3-44C0-AB9A-C82F6DE28770.jpeg)
173.2 KB120 views
Reply With Quote