Update on progress
Deck frame underway this week
Next week I’m running underground conduits for power and data to the deck.
Also running 2 x 50mm conduits under deck from laptop location in the NexDome bay unit to centre pier location for power and data cables to mount
Deck boards and trims to be completed late next week or early the week after
Expecting deck to be completed around the 18th December
|