So then, ran trench tape and filled that in, and ran the final conduit to the pier footing with 240V and 2 x CAT6 cables.

The levelled out the pad area, removing all the weeds, to a depth of 100mm. Also dug 400mm deep footing holes in the corners (actually some went much deeper) to cater for the longer term shed build.

Then popped on the reo, and tied it all together and popped it up on stand-offs, and then had the concrete delivered (by pump as the total area was going to use 7.4 cubic metres of concrete. Note also the installation of some drains to divert run-off from the hill.
Attached Thumbnails
Click for full-size image (IMG_1181.jpg)
86.1 KB53 views
Click for full-size image (IMG_1184.jpg)
95.6 KB55 views
Click for full-size image (IMG_1189.jpg)
92.2 KB51 views
Click for full-size image (IMG_1191.jpg)
82.1 KB53 views
Click for full-size image (IMG_1198.jpg)
97.3 KB51 views
Click for full-size image (IMG_1199.jpg)
70.1 KB64 views
Click for full-size image (IMG_1202.jpg)
67.0 KB60 views
Click for full-size image (IMG_1205.jpg)
64.1 KB58 views
Reply With Quote