From the wiki entry

Controversies Edit

Water quality concerns regarding the proximity of the seawater inlet to the desalination plant to the nearby sewage ocean outfall.[31] Environmental economists from the Australian National University studied the project after its completion and determined that "it was a costly decision that did not need to be made while dam levels were high." [32] In 2014, it was reported that the desalination plant was costing the taxpayers $534,246 per day as the plant sits idle. This was the price that the NSW Liberal-National Coalition government agreed upon when they set the 50-year lease with the plant's owners upon privatisation in 2011. To turn off the desalination plant all together would cost an extra $50 million.[33]

.......

Five hundred grand a day?
Can that be correct.

Alex