Update Day 4 of Build

This weekend we managed to install the Solar panel and roughed in the power, a stud wall to separate the Ob from the garage.

I wish i had of bought the nail gun for phase 1.... All i am saying!

The flashing is now complete with a nice test with some tropical style rain after we installed the flashing, great news is the ob was dry as a (insert really dry thing here)

it will be a few weeks before I get up, however I have the winch and cable and pulleys ready to go for the first live run.

Progress is on track with a few suprises. Planning is the key.