There has been some good progress this week, however photos will have to follow later on, when weather permits. The top frame has been constructed and moved from the backyard to the second floor, which proved quite the problem as it was too wide for our staircases. So we pulled it up by rope from the balcony. Yesterday, the frame was placed and the hinges installed, so the top can now flip open. I also installed the roof and I'm now ready to start applying the shiplap to the rest of the structure, which is something I can hopefully do in some dry hours in the evenings this week. The roof also need some finishings to be taken care off, and the back wall panel has to be constructed, but I will probably do that last. Electricity will then have to be installed, and after painting some of the remaining parts of the pier and pier adapter, my equipment can be placed. All looking very good at the moment.
|