Yep. On a flat site: Hire an mini excavator / two person drill to drill four 350/ 400 holes to refusal. Fill with concrete to 350 below floor level with starter bars. Join with excavated footings . Fully Reinforce and pour slab and footings in one piece. Chemset steel pier to slab. Easier if you know how deep required before you start. So drill / dig a test pit first and/ or ask an engineer for a site classification.
|